Road Improvement Program

Completed GoMC-PMTS-2024-9070
Project Description

Road opening  and grading  on selected roads across the ward 

Budget & Expenditure
Approved
KES 3.43M
Contract
KES 3.43M
Spent
KES 3.29M
Utilisation
95.9%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-9070
  • WardKitise/Kithuki
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start10 Apr 2024
  • End30 Jun 2024
Timeline
Cabinet Paper Approved
Phase One · 06 Feb 2024
Approved Requisition
Phase Two · 08 Feb 2024
Floated
Phase Two · 22 Feb 2024
Awarded
Phase Two · 04 Apr 2024
Site Handover
Phase Three · 04 Apr 2024
Not Started
Phase Two · 04 Apr 2024
Ongoing
Phase Three · 10 Apr 2024
Completed
Phase Three · 24 Jun 2024