Kwa Daina Mavindini Pipeline Improvement

Completed GoMC-PMTS-2024-6875
Budget & Expenditure
Approved
KES 2.34M
Contract
KES 2.62M
Spent
KES 2.61M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-6875
  • WardMtito Andei
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start01 Feb 2024
  • End03 Apr 2024
Timeline
Cabinet Paper Approved
Phase One · 09 Nov 2023
Approved Requisition
Phase Two · 20 Nov 2023
Refloated
Phase One · 13 Dec 2023
Awarded
Phase Two · 09 Jan 2024
Site Handover
Phase Three · 12 Feb 2024
Not Started
Phase Two · 02 Feb 2024
Ongoing
Phase Three · 19 Feb 2024
Completed
Phase Three · 25 Mar 2024