Kwa Daina Mavindini Pipeline Improvement
Home
Projects
Detail
Completed
GoMC-PMTS-2024-6875
Print
Share
Budget & Expenditure
Approved
KES 2.34M
Contract
KES 2.62M
Spent
KES 2.61M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Name
Contact
Subject
*
Message
*
Attachment
(optional — image or PDF, max 5MB)
Submit
Project Details
Ref
GoMC-PMTS-2024-6875
Ward
Mtito Andei
Sub-County
Kibwezi East
Department
Department of Water and Sanitation
Directorate
Water and Sanitation
FY
2023/2024
Source
Exchequer
Funded From
Ward
Category
Non Flagship
Start
01 Feb 2024
End
03 Apr 2024
Timeline
Cabinet Paper Approved
Phase One · 09 Nov 2023
Approved Requisition
Phase Two · 20 Nov 2023
Refloated
Phase One · 13 Dec 2023
Awarded
Phase Two · 09 Jan 2024
Site Handover
Phase Three · 12 Feb 2024
Not Started
Phase Two · 02 Feb 2024
Ongoing
Phase Three · 19 Feb 2024
Completed
Phase Three · 25 Mar 2024
Related Projects
Yekanga Borehole - Drilling,equipping And Distribution
Ongoing
Mulala Primary Borehole - Borehole Drilling And Develop
Ongoing
Water Improvement Program -kee
Ongoing
Water Improvement Program- Mavindini
Under Procurement