Ndueni-mulima Water Project

Completed GoMC-PMTS-2024-5043
Project Description

Rehabilitation of Mulima - Ndueni water distribution network

Budget & Expenditure
Approved
KES 4.90M
Contract
KES 4.90M
Spent
KES 4.75M
Utilisation
97%
Budget Utilisation
Gallery (1 photos)
Mulima Earthdam
Mulima Earthdam
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5043
  • WardMbooni
  • Sub-CountyMbooni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start04 Jun 2024
  • End04 Sep 2024
Timeline
Cabinet Paper Approved
Phase One · 17 Apr 2024
Approved Requisition
Phase Two · 18 Apr 2024
Refloated
Phase One · 07 May 2024
Awarded
Phase Two · 30 May 2024
Site Handover
Phase Three · 04 Jun 2024
Not Started
Phase Two · 04 Jun 2024
Ongoing
Phase Three · 10 Jun 2024
Completed
Phase Three · 04 Dec 2024