Ilengeni Water Project
Home
Projects
Detail
Completed
GoMC-PMTS-2024-4312
Print
Share
Project Description
Intake and treatment works, pumping systems, pipeline, water points and storage
Budget & Expenditure
Approved
KES 6.87M
Contract
KES 5.90M
Spent
KES 5.90M
Utilisation
85.9%
Budget Utilisation
Gallery (1 photos)
Ilengeni Water Project
Citizen Feedback
Name
Contact
Subject
*
Message
*
Attachment
(optional — image or PDF, max 5MB)
Submit
Project Details
Ref
GoMC-PMTS-2024-4312
Ward
Mbitini
Sub-County
Makueni
Department
Department of Water and Sanitation
Directorate
Water and Sanitation
FY
2023/2024
Source
Exchequer
Funded From
Ward
Category
Non Flagship
Start
15 May 2024
End
30 Oct 2024
Timeline
Cabinet Paper Approved
Phase One · 15 Mar 2024
Approved Requisition
Phase Two · 25 Mar 2024
Floated
Phase Two · 02 Apr 2024
Awarded
Phase Two · 09 May 2024
Site Handover
Phase Three · 10 May 2024
Not Started
Phase Two · 10 May 2024
Ongoing
Phase Three · 10 May 2024
Completed
Phase Three · 20 Dec 2024
Related Projects
Yekanga Borehole - Drilling,equipping And Distribution
Ongoing
Mulala Primary Borehole - Borehole Drilling And Develop
Ongoing
Water Improvement Program -kee
Ongoing
Water Improvement Program- Mavindini
Under Procurement