Planning and survey of Kalawa market

Completed GoMC-PMTS-2024-8122
Project Description
  • Preparation of local physical development plan
Budget & Expenditure
Approved
KES 1.00M
Contract
KES 1.00M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8122
  • WardKalawa
  • Sub-CountyMbooni
  • DepartmentDepartment of Lands, Urban Planning and Developmen
  • DirectorateLands, Urban Planning and Development
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start18 Dec 2023
  • End01 Apr 2024
Timeline
Cabinet Paper Approved
Phase One · 04 Sep 2023
Approved Requisition
Phase Two · 22 Sep 2023
Floated
Phase Two · 11 Oct 2023
Awarded
Phase Two · 11 Dec 2023
Site Handover
Phase Three · 11 Dec 2023
Not Started
Phase Two · 11 Dec 2023
Ongoing
Phase Three · 18 Dec 2023
Completed
Phase Three · 30 Aug 2024