Kwa Kamende Borehole

Completed GoMC-PMTS-2024-5983
Project Description

Solarization, installation of new pumpset, rehabilitation of pump house and fencing

Budget & Expenditure
Approved
KES 3.92M
Contract
KES 3.80M
Spent
KES 3.80M
Utilisation
96.8%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5983
  • WardWote/Nziu
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start27 Nov 2023
  • End15 Feb 2024
Timeline
Cabinet Paper Approved
Phase One · 18 Sep 2023
Approved Requisition
Phase Two · 25 Sep 2023
Floated
Phase Two · 19 Oct 2023
Awarded
Phase Two · 14 Nov 2023
Site Handover
Phase Three · 03 Jan 2024
Not Started
Phase Two · 03 Jan 2024
Ongoing
Phase Three · 15 Jan 2024
Completed
Phase Three · 02 Apr 2024