Kamunyolo Earth Dam

Completed GoMC-PMTS-2024-6643
Project Description

Operationalization of distribution line to Wote, installation of new pumpset, rehabilitation of raising main. Operationalization of Mwambani pipeline, installation of new pumpset, fencing, treatment plant, pipeline extension of 1.1km and connection to KPLC

Budget & Expenditure
Approved
KES 2.50M
Contract
KES 1.38M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-6643
  • WardWote/Nziu
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
  • Start03 Jun 2024
  • End31 Aug 2024
Timeline
Cabinet Paper Approved
Phase One · 15 Apr 2024
Approved Requisition
Phase Two · 15 Apr 2024
Floated
Phase Two · 24 Apr 2024
Awarded
Phase Two · 31 May 2021
Site Handover
Phase Three · 03 Jun 2024
Not Started
Phase Two · 03 Jun 2024
Ongoing
Phase Three · 03 Jun 2024
Completed
Phase Three · 30 May 2024