Yekanga Borehole

Completed GoMC-PMTS-2024-4716
Project Description

Drilling

Budget & Expenditure
Approved
KES 1.96M
Contract
KES 1.11M
Spent
KES 1.96M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-4716
  • WardMavindini
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start05 Feb 2024
  • End18 Mar 2024
Timeline
Cabinet Paper Approved
Phase One · 30 Oct 2023
Approved Requisition
Phase Two · 18 Dec 2023
Floated
Phase Two · 22 Dec 2023
Awarded
Phase Two · 31 Jan 2024
Site Handover
Phase Three · 01 Feb 2024
Not Started
Phase Two · 01 Feb 2024
Ongoing
Phase Three · 01 Feb 2024
Completed
Phase Three · 20 May 2024