Ngaa Borehole

Completed GoMC-PMTS-2024-8270
Project Description

Drilling and Caping

Budget & Expenditure
Approved
KES 1.50M
Contract
KES 2.60M
Spent
KES 2.60M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8270
  • WardNzaui/Kilili/Kalamba
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start03 Jan 2024
  • End03 Apr 2024
Timeline
Cabinet Paper Approved
Phase One · 07 Sep 2023
Approved Requisition
Phase Two · 18 Oct 2023
Refloated
Phase One · 27 Nov 2023
Awarded
Phase Two · 29 Dec 2023
Site Handover
Phase Three · 30 Dec 2023
Not Started
Phase Two · 30 Dec 2023
Ongoing
Phase Three · 30 Dec 2023
Completed
Phase Three · 16 Dec 2024