Construction Of Sump Tank Reservoir, Water Treatment And Distribution To 10 Clusters From Athi River Water

Completed GoMC-PMTS-2024-9499
Budget & Expenditure
Approved
KES 1.41M
Contract
KES 0.00
Spent
KES 1.41M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-9499
  • WardKikumbulyu North
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
Timeline
Completed
Phase Three · 28 Oct 2024