Katoloni Pipeline Extension

Completed GoMC-PMTS-2024-8816
Project Description

Pipeline extension to Katoloni market, construction of tank Platform, water kiosk and storage tank 1000lts

Budget & Expenditure
Approved
KES 980.0K
Contract
KES 949.5K
Spent
KES 949.0K
Utilisation
96.8%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8816
  • WardWote/Nziu
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start10 Dec 2023
  • End31 Mar 2024
Timeline
Cabinet Paper Approved
Phase One · 24 Oct 2023
Approved Requisition
Phase Two · 27 Oct 2023
Floated
Phase Two · 08 Nov 2024
Awarded
Phase Two · 06 Dec 2023
Site Handover
Phase Three · 13 Dec 2023
Not Started
Phase Two · 13 Dec 2023
Ongoing
Phase Three · 20 Dec 2023
Completed
Phase Three · 25 Jan 2024