Water Improvement And Borehole Maintenance

Completed GoMC-PMTS-2024-1319
Budget & Expenditure
Approved
KES 524.2K
Contract
KES 284.5K
Spent
KES 278.5K
Utilisation
53.1%
Budget Utilisation
Citizen Feedback
James Makau Nzioka 08 May 2024
Water Borehole At Kyumbe Primary School

I Helped Sink A Borehole At Kyumbe Primary School Through My Friends From The Usa. It Has Been Hard To Get County Support In Getting The Recipients Benefit From This Water After It Was "claimed" That It Was Sunk By The Country Through The Former Governor. I Have Tried Reaching Out But It Has Proved Very Difficult To Get An Audience With Any Official. Is There Anyone I Can Reach Out And Get An Audience?

Official Response:

Hello James Makau. The borehole has 2m3/hr, just enough for the school only. It cannot be distributed further. Thank you

Project Details
  • RefGoMC-PMTS-2024-1319
  • WardKathonzweni
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start10 Mar 2024
  • End30 Apr 2024
Timeline
Cabinet Paper Approved
Phase One · 05 Jan 2024
Approved Requisition
Phase Two · 12 Jan 2024
Floated
Phase Two · 29 Jan 2024
Awarded
Phase Two · 26 Feb 2024
Site Handover
Phase Three · 27 Feb 2024
Not Started
Phase Two · 27 Feb 2024
Ongoing
Phase Three · 04 Mar 2024
Completed
Phase Three · 15 Mar 2024