Kasikeu Stock Yard And Toilet.

Completed GoMC-PMTS-2024-6034
Project Description

Rehabilitation of Kasikeu stock yard and toilet.

Budget & Expenditure
Approved
KES 478.2K
Contract
KES 2.70M
Spent
KES 470.0K
Utilisation
98.3%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-6034
  • WardKasikeu
  • Sub-CountyKilome
  • DepartmentDepartment of Agriculture, Livestock, Fisheries &
  • DirectorateLivestock and Fisheries Development
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start15 Apr 2024
  • End30 May 2024
Timeline
Cabinet Paper Approved
Phase One · 17 Sep 2020
Approved Requisition
Phase Two · 27 Feb 2024
Floated
Phase Two · 18 Mar 2024
Awarded
Phase Two · 15 Apr 2024
Site Handover
Phase Three · 15 Apr 2024
Not Started
Phase Two · 15 Apr 2024
Ongoing
Phase Three · 15 Apr 2024
Completed
Phase Three · 30 Jun 2024