Nziu Playground

Completed GoMC-PMTS-2024-6715
Project Description

Levelling and goal posts installation

Budget & Expenditure
Approved
KES 1.50M
Contract
KES 1.74M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-6715
  • WardWote/Nziu
  • Sub-CountyMakueni
  • DepartmentDepartment of Gender, Children, Youth, Sports and
  • DirectorateSports
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start08 Mar 2024
  • End08 May 2024
Timeline
Cabinet Paper Approved
Phase One · 31 Aug 2023
Approved Requisition
Phase Two · 04 Jan 2024
Floated
Phase Two · 05 Feb 2024
Awarded
Phase Two · 08 Mar 2024
Site Handover
Phase Three · 08 Mar 2024
Not Started
Phase Two · 08 Mar 2024
Ongoing
Phase Three · 08 Mar 2024
Completed
Phase Three · 27 Sep 2024