Drilling Of Ngaamba Borehole

Completed GoMC-PMTS-2024-2095
Project Description

i. Equipping the Borehole with Pump and Solar 
ii. Construction of 1No. Water Kiosk
iii. 1No. 10m3 plastic tank on a platform

Budget & Expenditure
Approved
KES 2.98M
Contract
KES 2.82M
Spent
KES 1.97M
Utilisation
66.3%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-2095
  • WardNguumo
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start20 Mar 2024
  • End01 Mar 2004
Timeline
Cabinet Paper Approved
Phase One · 20 Dec 2023
Approved Requisition
Phase Two · 22 Dec 2023
Floated
Phase Two · 08 Feb 2024
Awarded
Phase Two · 08 Mar 2024
Site Handover
Phase Three · 18 Mar 2024
Not Started
Phase Two · 18 Mar 2024
Ongoing
Phase Three · 26 Mar 2024
Completed
Phase Three · 14 Jun 2024