Katangini Water Project

Completed GoMC-PMTS-2024-8047
Project Description

i. Laying, jointing, backfilling and testing of 4km DN63 HDPE pipeline 
ii. Rehabilitation of 1No water Kiosk
iii. 2No. tank Platforms
iv. 3 no 10m3 plastic tanks
v. Construction of 3 communal water points (One for Kaasya primary)

Budget & Expenditure
Approved
KES 2.99M
Contract
KES 2.37M
Spent
KES 2.30M
Utilisation
76.9%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8047
  • WardNguu/Masumba
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start10 Dec 2023
  • End31 Mar 2024
Timeline
Cabinet Paper Approved
Phase One · 28 Sep 2023
Approved Requisition
Phase Two · 05 Oct 2024
Floated
Phase Two · 07 Nov 2023
Awarded
Phase Two · 08 Dec 2023
Site Handover
Phase Three · 19 Dec 2023
Not Started
Phase Two · 19 Dec 2023
Ongoing
Phase Three · 22 Dec 2023
Completed
Phase Three · 24 Apr 2024