Construction Of Kathyaka Masonry Tank/ Under Kibmawasco

Completed GoMC-PMTS-2024-8001
Project Description

. Rehabilitation of Kathyaka – Nyayo water pipeline extension 1.32km
ii. Cutline Makaani  pipeline extension 4km 

Budget & Expenditure
Approved
KES 4.41M
Contract
KES 4.23M
Spent
KES 4.23M
Utilisation
95.9%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8001
  • WardKikumbulyu North
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start22 Jan 2024
  • End22 May 2024
Timeline
Cabinet Paper Approved
Phase One · 09 Nov 2023
Approved Requisition
Phase Two · 20 Nov 2023
Floated
Phase Two · 04 Dec 2023
Awarded
Phase Two · 03 Jan 2024
Site Handover
Phase Three · 04 Jan 2024
Not Started
Phase Two · 04 Jan 2024
Ongoing
Phase Three · 04 Jan 2024
Completed
Phase Three · 10 Dec 2024