Improvement Of Water In Kikumbulyu North Ward By Kibmawasco-kasayani Market To Cutline, Kwa Kakumi To Kwa Rose Muambani, Kasayani Market To Kwa Presillah Mutinda , Ndetani Ccti To Aic Kalinga To Kwa Kitheka, Kathyaka Market To Kilisa To King’uutheni And Nyayo Market To Soko Muyo

Completed GoMC-PMTS-2024-7330
Project Description

. Rehabilitation of Kathyaka – Nyayo water pipeline extension 1.32km
ii. Cutline Makaani  pipeline extension 4km 

Budget & Expenditure
Approved
KES 4.30M
Contract
KES 2.30M
Spent
KES 2.30M
Utilisation
53.5%
Budget Utilisation
Gallery (1 photos)
Kikumbulyu North Water Tanks
Kikumbulyu North Water Tanks
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-7330
  • WardKikumbulyu North
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start06 May 2024
  • End15 Aug 2024
Timeline
Cabinet Paper Approved
Phase One · 28 Sep 2023
Approved Requisition
Phase Two · 28 Sep 2023
Floated
Phase Two · 18 Apr 2023
Awarded
Phase Two · 23 Apr 2024
Site Handover
Phase Three · 16 May 2024
Not Started
Phase Two · 16 May 2024
Ongoing
Phase Three · 20 May 2024
Completed
Phase Three · 10 Dec 2024