Kimawasco Line Extension-mbeetwani (water)

Completed GoMC-PMTS-2024-1194
Project Description

i. 2.2km DN63 HDPE line
ii. Construction of 1No. Water kiosk at Mbeetwani

Budget & Expenditure
Approved
KES 1.50M
Contract
KES 1.40M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1194
  • WardKikumbulyu South
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start09 Apr 2024
  • End09 Jul 2024
Timeline
Cabinet Paper Approved
Phase One · 28 Sep 2023
Approved Requisition
Phase Two · 29 Feb 2024
Refloated
Phase One · 04 Mar 2024
Awarded
Phase Two · 21 Mar 2024
Site Handover
Phase Three · 18 Apr 2024
Not Started
Phase Two · 18 Apr 2024
Ongoing
Phase Three · 24 Apr 2024
Completed
Phase Three · 31 May 2024