Sekeleni Earthdam

Completed GoMC-PMTS-2024-5215
Project Description

i. Embankment shaping
ii.  Desilting  
iii. Spillway protection

Budget & Expenditure
Approved
KES 3.43M
Contract
KES 3.30M
Spent
KES 3.30M
Utilisation
96.2%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5215
  • WardNguumo
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start15 Dec 2023
  • End31 Mar 2024
Timeline
Cabinet Paper Approved
Phase One · 18 Sep 2023
Approved Requisition
Phase Two · 25 Sep 2023
Refloated
Phase One · 19 Oct 2023
Awarded
Phase Two · 20 Nov 2023
Site Handover
Phase Three · 21 Nov 2023
Not Started
Phase Two · 21 Nov 2023
Ongoing
Phase Three · 25 May 2023
Completed
Phase Three · 27 Nov 2024