Kimia-kateiko Water Project-water Distribution. Extension Of The Pipeline For 4kms

Completed GoMC-PMTS-2024-1756
Project Description

i. Laying, jointing, backfilling and testing of 2.6km DN63 rising mai
ii. Construction of 1No water kiosk
iii. Construction of 10m high steel tower with 3no. 10m3 plastic tanks 

Budget & Expenditure
Approved
KES 4.90M
Contract
KES 4.75M
Spent
KES 4.72M
Utilisation
96.4%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1756
  • WardNguu/Masumba
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start20 Feb 2024
  • End31 May 2024
Timeline
Cabinet Paper Approved
Phase One · 09 Nov 2023
Approved Requisition
Phase Two · 23 Nov 2023
Floated
Phase Two · 17 Jan 2024
Awarded
Phase Two · 14 Feb 2024
Site Handover
Phase Three · 19 Feb 2024
Not Started
Phase Two · 19 Feb 2024
Ongoing
Phase Three · 25 Feb 2024
Completed
Phase Three · 26 Mar 2024
Completed
Phase Three · 26 Mar 2024
Completed
Phase Three · 26 Mar 2024