Rehabilitation Of Stalled Boreholes In The Ward ( Kwa Kimulu, Kiiwai, Emali, Nduuduni Etc)

Completed GoMC-PMTS-2024-3502
Project Description

i. Flushing and Test Pumping of Maatha Borehole
ii. Flushing and Test Pumping of Kiuani Borehole
iii. Replacement of 1No Inverter in Mulala borehole

Budget & Expenditure
Approved
KES 1.96M
Contract
KES 1.11M
Spent
KES 1.11M
Utilisation
56.8%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3502
  • WardEmali/Mulala
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start01 Mar 2024
  • End30 Apr 2024
Timeline
Cabinet Paper Approved
Phase One · 22 Jan 2024
Cabinet Paper Approved
Phase One · 22 Jan 2024
Approved Requisition
Phase Two · 24 Jan 2024
Floated
Phase Two · 01 Feb 2024
Awarded
Phase Two · 26 Feb 2024
Site Handover
Phase Three · 28 Feb 2024
Not Started
Phase Two · 28 Feb 2024
Ongoing
Phase Three · 01 Mar 2024
Completed
Phase Three · 20 Mar 2024