Kikwasuni Ecde

Completed GoMC-PMTS-2024-2547
Project Description
  • 1No. ECDE Classroom with an office and Store
  • 3-Door Pit Latrine with Urinal
  • 1No. Wooden Desk
  • 1No. Wooden Arm Chair
  • 20 No. Kiddy chairs
  • 10 No. Kiddy tables
  • Water harvesting goods (5,000Ltrs Water Tank and base)
  • Electrical Works (electrical conduits only)
  • Display Pinned board
  • Branding, Publicity and Signwriting
  • Blackboard
Budget & Expenditure
Approved
KES 2.45M
Contract
KES 2.37M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-2547
  • WardIvingoni/Nzambani
  • Sub-CountyKibwezi East
  • DepartmentDepartment of ICT, Education and Internship
  • DirectorateECDE, Support to Education and Library Services
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start28 Feb 2024
  • End28 May 2024
Timeline
Cabinet Paper Approved
Phase One · 15 Oct 2023
Approved Requisition
Phase Two · 18 Oct 2023
Floated
Phase Two · 22 Jan 2024
Awarded
Phase Two · 28 Feb 2024
Site Handover
Phase Three · 08 Mar 2024
Not Started
Phase Two · 08 Mar 2024
Ongoing
Phase Three · 15 Mar 2024
Completed
Phase Three · 10 Sep 2024