Drilling And Equipping Of 5 No. Boreholes In The Ward Using Own Machines

Completed GoMC-PMTS-2024-1493
Budget & Expenditure
Approved
KES 7.00M
Contract
KES 4.92M
Spent
KES 4.77M
Utilisation
68.1%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1493
  • WardKalawa
  • Sub-CountyMbooni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start19 Nov 2023
  • End04 Dec 2023
Timeline
Cabinet Paper Approved
Phase One · 31 Aug 2023
Approved Requisition
Phase Two · 18 Sep 2023
Floated
Phase Two · 24 Oct 2023
Awarded
Phase Two · 17 Nov 2023
Site Handover
Phase Three · 18 Nov 2023
Not Started
Phase Two · 18 Nov 2023
Ongoing
Phase Three · 19 Nov 2023
Completed
Phase Three · 04 Dec 2023