Ulilinzi Ecde

Completed GoMC-PMTS-2024-1899
Project Description
  • 1No. ECDE Classroom
  • 1No.lockable metallic cabinet
  • 1No. Wooden Desk
  • 1No. Wooden Arm Chair
  • Water harvesting goods (5,000Ltrs Water Tank and Base)
  • Full Electrical Works
  • Display Pinned board
  • Branding, Publicity and Signwriting

Budget & Expenditure
Approved
KES 1.47M
Contract
KES 1.41M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1899
  • WardMasongaleni
  • Sub-CountyKibwezi East
  • DepartmentDepartment of ICT, Education and Internship
  • DirectorateECDE, Support to Education and Library Services
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start14 Mar 2024
  • End14 Jun 2024
Timeline
Cabinet Paper Approved
Phase One · 25 Oct 2023
Approved Requisition
Phase Two · 05 Dec 2023
Floated
Phase Two · 13 Jan 2024
Awarded
Phase Two · 14 Mar 2024
Site Handover
Phase Three · 14 Mar 2024
Not Started
Phase Two · 14 Mar 2024
Ongoing
Phase Three · 14 Mar 2024
Completed
Phase Three · 25 Jun 2024