Mikuyu II Water Project

Completed GoMC-PMTS-2024-2605
Project Description

Phased scopes:
i. Pumping system rehabilitation.
ii. Rising main rehabilitation.
iii.    Installation of a 1.4km HDPE & GI pipeline through Uvilani to Kayumbi.
Iv.    Construction of a Kiosk at Kwa Kivuthi in Kayumbi area.

Budget & Expenditure
Approved
KES 1.47M
Contract
KES 496.5K
Spent
KES 496.5K
Utilisation
33.8%
Budget Utilisation
Citizen Feedback
Moses Mutuku 28 Nov 2024
Mikuyu Ii Water Project

Poorly Done And It Has No
water. 1.47 Million Wasted/ Stolen

Official Response:

Thank you Moses, we acknowledge your concerns. We wish to clarify the situation as follow in order to provide a clear understanding of the ongoing efforts by the County Government:
The old project sump was severely affected by the March-April-May floods, which rendered it non-functional. However, the PMC retrieved the pump and stored it securely to prevent further damage. In response to the setback, the government allocated funds in the current Financial Year to construct a new sump and extend water distribution to the Kasikeu Dispensary.
To ensure the construction is done effectively and sustainably, the project is scheduled to commence immediately after the October-November-December rains to avoid similar weather-related setbacks. Currently, the project is in the procurement stage and we are working diligently to ensure its timely completion. We remain committed to delivering quality and sustainable solutions while upholding transparency and accountability. Thank you for your patience and understanding as we work to address this matter.

Project Details
  • RefGoMC-PMTS-2024-2605
  • WardKasikeu
  • Sub-CountyKilome
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start08 Feb 2024
  • End12 Mar 2024
Timeline
Cabinet Paper Approved
Phase One · 20 Nov 2023
Approved Requisition
Phase Two · 20 Nov 2023
Floated
Phase Two · 18 Dec 2023
Awarded
Phase Two · 31 Jan 2024
Site Handover
Phase Three · 13 Feb 2024
Not Started
Phase Two · 13 Feb 2024
Ongoing
Phase Three · 15 Feb 2024
Completed
Phase Three · 07 Mar 2024