Katatu Dam

Completed GoMC-PMTS-2024-2910
Project Description

i.    Desilting and expansion of the reservoir
ii.    Making good of the spillway and embankment
iii.    Construction of a check dams and cut off drains.

Budget & Expenditure
Approved
KES 3.92M
Contract
KES 3.80M
Spent
KES 3.68M
Utilisation
94%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-2910
  • WardKiima Kiu/Kalanzoni
  • Sub-CountyKilome
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start10 Nov 2023
  • End30 Jan 2024
Timeline
Cabinet Paper Approved
Phase One · 07 Sep 2024
Approved Requisition
Phase Two · 18 Sep 2023
Floated
Phase Two · 06 Oct 2024
Awarded
Phase Two · 01 Nov 2023
Site Handover
Phase Three · 16 Nov 2024
Not Started
Phase Two · 16 Nov 2024
Ongoing
Phase Three · 12 Nov 2024
Completed
Phase Three · 20 Dec 2024