Mavindini Ecde

Completed GoMC-PMTS-2024-2784
Project Description
  • 1No. ECDE Classroom with an office and Store
  • 1No.lockable metallic cabinet
  • 1No. Wooden Desk
  • 1No. Wooden Arm Chair
  • Water harvesting goods (5,000Ltrs Water Tank and base)
  • Electrical Works (conduits only)
  •  Display Pinned board
  • 20 No. Kiddy chairs
  • 10 No. Kiddy tables
  • Branding, Publicity and Signwriting
  • 1No. whiteboard
  • 1No. blackboard
  • 2 No. duster
  • 10 No. Mark pens
  • Shelves
Budget & Expenditure
Approved
KES 1.96M
Contract
KES 3.28M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-2784
  • WardMtito Andei
  • Sub-CountyKibwezi East
  • DepartmentDepartment of ICT, Education and Internship
  • DirectorateECDE, Support to Education and Library Services
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start19 Jan 2024
  • End19 Apr 2024
Timeline
Cabinet Paper Approved
Phase One · 15 Oct 2023
Approved Requisition
Phase Two · 18 Oct 2023
Floated
Phase Two · 22 Dec 2023
Awarded
Phase Two · 19 Jan 2024
Site Handover
Phase Three · 05 Feb 2024
Not Started
Phase Two · 05 Feb 2024
Ongoing
Phase Three · 10 Feb 2024
Completed
Phase Three · 04 Jun 2024