Youth Empowerment Programme -kithungo/kitundu

Completed GoMC-PMTS-2024-2974
Budget & Expenditure
Approved
KES 900.0K
Contract
KES 843.9K
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-2974
  • WardKithungo/Kitundu
  • Sub-CountyMbooni
  • DepartmentDepartment of Gender, Children, Youth, Sports and
  • DirectorateYouth
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start21 Jun 2024
  • End19 Jul 2024
Timeline
Cabinet Paper Approved
Phase One · 20 May 2024
Approved Requisition
Phase Two · 20 May 2024
Floated
Phase Two · 31 May 2024
Awarded
Phase Two · 21 Jun 2024
Site Handover
Phase Three · 21 Jun 2024
Not Started
Phase Two · 21 Jun 2024
Ongoing
Phase Three · 21 Jun 2024
Completed
Phase Three · 03 Jun 2025