Kwa Matinga Water Project

Completed GoMC-PMTS-2024-3086
Project Description

Drilling of borehole, equipping and solarizing, construction of 1.0km rising main to kwa Matinga storage tank, rehabilitation of 3.4km distribution pipeline ,construction of 1No. water kiosk and installation 2No.5 cubic metres plastic storage tank

Budget & Expenditure
Approved
KES 4.79M
Contract
KES 4.60M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3086
  • WardKisau/Kiteta
  • Sub-CountyMbooni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start27 Dec 2023
  • End26 Apr 2024
Timeline
Cabinet Paper Approved
Phase One · 04 Sep 2023
Approved Requisition
Phase Two · 13 Oct 2023
Floated
Phase Two · 22 Nov 2023
Awarded
Phase Two · 18 Dec 2023
Site Handover
Phase Three · 15 Jan 2024
Not Started
Phase Two · 15 Jan 2024
Ongoing
Phase Three · 07 Feb 2024
Completed
Phase Three · 05 Sep 2024