Kwa Ivali Earthdam

Completed GoMC-PMTS-2024-3805
Project Description

Desiling reservoir and rehabilitation of spillway

Budget & Expenditure
Approved
KES 4.90M
Contract
KES 4.75M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3805
  • WardKalawa
  • Sub-CountyMbooni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start15 Mar 2024
  • End30 Jun 2024
Timeline
Cabinet Paper Approved
Phase One · 09 Nov 2023
Approved Requisition
Phase Two · 20 Nov 2023
Floated
Phase Two · 04 Feb 2024
Awarded
Phase Two · 08 Mar 2024
Site Handover
Phase Three · 20 Mar 2024
Not Started
Phase Two · 20 Mar 2024
Ongoing
Phase Three · 23 Mar 2024
Completed
Phase Three · 26 Jun 2024