Kwa Muthama Earthdam
Home
Projects
Detail
Completed
GoMC-PMTS-2024-5368
Print
Share
Project Description
Desilting Kwa Muthama Earthdam
Budget & Expenditure
Approved
KES 2.45M
Contract
KES 2.38M
Spent
KES 2.37M
Utilisation
96.9%
Budget Utilisation
Citizen Feedback
Name
Contact
Subject
*
Message
*
Attachment
(optional — image or PDF, max 5MB)
Submit
Project Details
Ref
GoMC-PMTS-2024-5368
Ward
Kalawa
Sub-County
Mbooni
Department
Department of Water and Sanitation
Directorate
Water and Sanitation
FY
2023/2024
Source
Exchequer
Funded From
Ward
Category
Non Flagship
Start
08 Jan 2024
End
12 Mar 2024
Timeline
Cabinet Paper Approved
Phase One · 09 Nov 2023
Approved Requisition
Phase Two · 20 Nov 2023
Floated
Phase Two · 30 Nov 2023
Awarded
Phase Two · 03 Jan 2024
Site Handover
Phase Three · 28 Jan 2024
Not Started
Phase Two · 12 Jan 2024
Ongoing
Phase Three · 03 Aug 2024
Completed
Phase Three · 01 Oct 2024
Related Projects
Yekanga Borehole - Drilling,equipping And Distribution
Ongoing
Mulala Primary Borehole - Borehole Drilling And Develop
Ongoing
Water Improvement Program -kee
Ongoing
Water Improvement Program- Mavindini
Under Procurement