Kwa Muthama Earthdam

Completed GoMC-PMTS-2024-5368
Project Description

Desilting Kwa Muthama Earthdam 

Budget & Expenditure
Approved
KES 2.45M
Contract
KES 2.38M
Spent
KES 2.37M
Utilisation
96.9%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5368
  • WardKalawa
  • Sub-CountyMbooni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start08 Jan 2024
  • End12 Mar 2024
Timeline
Cabinet Paper Approved
Phase One · 09 Nov 2023
Approved Requisition
Phase Two · 20 Nov 2023
Floated
Phase Two · 30 Nov 2023
Awarded
Phase Two · 03 Jan 2024
Site Handover
Phase Three · 28 Jan 2024
Not Started
Phase Two · 12 Jan 2024
Ongoing
Phase Three · 03 Aug 2024
Completed
Phase Three · 01 Oct 2024