Kooi Earth Dam

Completed GoMC-PMTS-2024-6165
Project Description

Kooi earth dam -   Desilting of the reservoir and construction of check dams

Budget & Expenditure
Approved
KES 4.90M
Contract
KES 4.77M
Spent
KES 475.9K
Utilisation
9.7%
Budget Utilisation
Gallery (1 photos)
Kooi Earthdam
Kooi Earthdam
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-6165
  • WardTulimani
  • Sub-CountyMbooni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start15 Feb 2024
  • End30 Jun 2024
Timeline
Cabinet Paper Approved
Phase One · 09 Nov 2023
Approved Requisition
Phase Two · 20 Nov 2023
Refloated
Phase One · 04 Jan 2024
Awarded
Phase Two · 02 Feb 2024
Site Handover
Phase Three · 12 Feb 2024
Not Started
Phase Two · 12 Feb 2024
Ongoing
Phase Three · 12 Feb 2024
Completed
Phase Three · 06 Mar 2024