Athi-miangeni- Kalawa Water Project.

Completed GoMC-PMTS-2024-9810
Project Description

Athi-Miangeni- Kalawa water project. Phase 1-Construction of pump house, treatment, pump the water to Wii hills and piping for distribution.

Budget & Expenditure
Approved
KES 1.00M
Contract
KES 950.0K
Spent
KES 950.0K
Utilisation
95%
Budget Utilisation
Gallery (1 photos)
Kalawa Water Project
Kalawa Water Project
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-9810
  • WardKalawa
  • Sub-CountyMbooni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start15 Mar 2024
  • End15 May 2024
Timeline
Cabinet Paper Approved
Phase One · 02 Feb 2024
Approved Requisition
Phase Two · 05 Apr 2024
Floated
Phase Two · 07 May 2024
Awarded
Phase Two · 03 Mar 2024
Site Handover
Phase Three · 10 Mar 2024
Not Started
Phase Two · 10 Mar 2024
Ongoing
Phase Three · 18 Apr 2024
Completed
Phase Three · 12 May 2024