Green Grams Value Chain Development

Completed GoMC-PMTS-2024-2618
Project Description

procurement of 1MT green grams seeds distributed to 1,000 beneficiarie & GAP trainings.

Budget & Expenditure
Approved
KES 2.50M
Contract
KES 2.23M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-2618
  • WardMtito Andei
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Agriculture, Livestock, Fisheries &
  • DirectorateAgriculture
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start25 Sep 2023
  • End06 Oct 2023
Timeline
Cabinet Paper Approved
Phase One · 31 Aug 2023
Approved Requisition
Phase Two · 14 Sep 2023
Floated
Phase Two · 12 Sep 2023
Awarded
Phase Two · 25 Sep 2023
Site Handover
Phase Three · 25 Sep 2023
Not Started
Phase Two · 25 Sep 2023
Ongoing
Phase Three · 25 Sep 2023
Completed
Phase Three · 24 Oct 2023