Makueni Child Protection Centre

Completed GoMC-PMTS-2024-9190
Project Description

Construction of a building, street lighting and land scaping

Budget & Expenditure
Approved
KES 6.35M
Contract
KES 3.94M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-9190
  • WardEmali/Mulala
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Gender, Children, Youth, Sports and
  • DirectorateGender, Children and Social Services
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start17 Apr 2024
  • End30 Aug 2024
Timeline
Cabinet Paper Approved
Phase One · 20 Dec 2023
Approved Requisition
Phase Two · 19 Feb 2024
Floated
Phase Two · 28 Feb 2024
Awarded
Phase Two · 17 Apr 2024
Site Handover
Phase Three · 09 May 2024
Not Started
Phase Two · 15 May 2024
Ongoing
Phase Three · 15 May 2024
Completed