Sports Development Mtito Andei

Completed GoMC-PMTS-2024-4731
Project Description

Purchase of sport items

Budget & Expenditure
Approved
KES 380.0K
Contract
KES 380.0K
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-4731
  • WardMtito Andei
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Gender, Children, Youth, Sports and
  • DirectorateSports
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start04 Dec 2023
  • End19 Jan 2024
Timeline
Cabinet Paper Approved
Phase One · 31 Aug 2023
Approved Requisition
Phase Two · 29 Sep 2023
Floated
Phase Two · 24 Oct 2023
Awarded
Phase Two · 04 Dec 2023
Site Handover
Phase Three · 04 Dec 2023
Not Started
Phase Two · 04 Dec 2023
Ongoing
Phase Three · 04 Dec 2023
Completed
Phase Three · 24 Jan 2024