Kyangoma Stadium

Completed GoMC-PMTS-2024-5272
Project Description

Levelling of the filed

Budget & Expenditure
Approved
KES 1.03M
Contract
KES 1.02M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Athanus Muendo 07 May 2024
Kyangoma Stadium

The Project Is Stalk

Attachment
Official Response:

From the Directorate of Sports: The contractor had paused the project due to rains and has since reported back to site to ensure completion of the project. Thank you for your feedback.

Project Details
  • RefGoMC-PMTS-2024-5272
  • WardMbooni
  • Sub-CountyMbooni
  • DepartmentDepartment of Gender, Children, Youth, Sports and
  • DirectorateSports
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start13 Feb 2024
  • End13 Apr 2024
Timeline
Cabinet Paper Approved
Phase One · 31 Aug 2023
Approved Requisition
Phase Two · 09 Nov 2023
Floated
Phase Two · 19 Dec 2023
Awarded
Phase Two · 13 Feb 2024
Site Handover
Phase Three · 01 Mar 2024
Not Started
Phase Two · 01 Mar 2024
Ongoing
Phase Three · 08 Mar 2024
Completed
Phase Three · 13 Sep 2024