Levelling of the field and construction of a toilet

Budget & Expenditure
Approved
KES 2.00M
Contract
KES 2.00M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1349
  • WardKiima Kiu/Kalanzoni
  • Sub-CountyKilome
  • DepartmentDepartment of Gender, Children, Youth, Sports and
  • DirectorateSports
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start14 Mar 2024
  • End14 May 2024
Timeline
Cabinet Paper Approved
Phase One · 31 Aug 2023
Approved Requisition
Phase Two · 04 Jan 2024
Floated
Phase Two · 19 Feb 2024
Awarded
Phase Two · 14 Mar 2024
Site Handover
Phase Three · 19 Mar 2024
Not Started
Phase Two · 19 Mar 2024
Ongoing
Phase Three · 25 Mar 2024
Completed
Phase Three · 18 Jul 2024