Muisyo-ngomeni River Drift

Completed GoMC-PMTS-2024-8701
Project Description

Construction of  100m by 5m Non-vented Reinforced Concrete drift

Budget & Expenditure
Approved
KES 9.82M
Contract
KES 8.35M
Spent
KES 8.35M
Utilisation
85.1%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8701
  • WardMbooni
  • Sub-CountyMbooni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start20 May 2024
  • End21 May 2024
Timeline
Cabinet Paper Approved
Phase One · 20 Sep 2023
Approved Requisition
Phase Two · 07 Dec 2023
Refloated
Phase One · 02 Sep 2023
Awarded
Phase Two · 03 May 2024
Site Handover
Phase Three · 20 May 2024
Not Started
Phase Two · 20 May 2024
Ongoing
Phase Three · 21 May 2024
Completed
Phase Three · 14 Oct 2024