Purified Drinking Water Production

Completed GoMC-PMTS-2024-5520
Project Description

 purification and package water

Budget & Expenditure
Approved
KES 1.51M
Contract
KES 1.39M
Spent
KES 1.39M
Utilisation
91.9%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5520
  • WardHeadquaters
  • Sub-CountyHeadquarters
  • DepartmentDepartment of Agriculture, Livestock, Fisheries &
  • DirectorateMakueni Fruit Develoment and Marketing Authority
  • FY2023/2024
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
  • Start29 May 2024
  • End26 Aug 2024
Timeline
Cabinet Paper Approved
Phase One · 07 Sep 2023
Approved Requisition
Phase Two · 03 May 2024
Floated
Phase Two · 03 May 2024
Awarded
Phase Two · 28 May 2024
Site Handover
Phase Three · 26 Aug 2024
Not Started
Phase Two · 26 Aug 2024
Ongoing
Phase Three · 29 May 0004
Completed
Phase Three · 27 Aug 2024