Mang’elete Borehole (Changed to equip Kalekye borehole)

Completed GoMC-PMTS-2024-5335
Project Description

Drilling and Equipping (solarization, kiosk, tank) of Mang’elete Borehole

Budget & Expenditure
Approved
KES 2.94M
Contract
KES 738.5K
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5335
  • WardIvingoni/Nzambani
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start30 Nov 2023
  • End30 Dec 2023
Timeline
Cabinet Paper Approved
Phase One · 07 Sep 2023
Approved Requisition
Phase Two · 18 Oct 2023
Floated
Phase Two · 27 Oct 2023
Awarded
Phase Two · 28 Nov 2023
Site Handover
Phase Three · 09 May 2024
Not Started
Phase Two · 09 May 2024
Ongoing
Phase Three · 13 May 2024
Completed
Phase Three · 28 Jun 2024