Equipment Hire For Desilting Earth Dams(kwa Kitwa,kwa Manza, Kwa Kasau And Victoria Earth Dams)

Completed GoMC-PMTS-2024-9453
Project Description

Scope change to desilt Kwa Mutungwa earth dam)

Budget & Expenditure
Approved
KES 2.94M
Contract
KES 2.9K
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-9453
  • WardMtito Andei
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start11 Dec 2023
  • End05 Mar 2024
Timeline
Cabinet Paper Approved
Phase One · 18 Sep 2023
Approved Requisition
Phase Two · 18 Sep 2024
Floated
Phase Two · 25 Sep 2023
Awarded
Phase Two · 05 Dec 2023
Site Handover
Phase Three · 20 Dec 2023
Not Started
Phase Two · 20 Dec 2023
Ongoing
Phase Three · 20 Dec 2023
Completed
Phase Three · 19 Jun 2024