Kaiti Miting'ani Sand Dam : Construction Of Sump, Increase Sand Dam Height By 1.5m And Construction Of Raised Main Ms Panel Tank At Yiumo Kwa Mukosi

Completed GoMC-PMTS-2024-8693
Project Description

Raising of sand dam wall, construction of 100Cu.M Sump Tank, Construction of Yiumo Elevated 50Cu.M steel tank

Budget & Expenditure
Approved
KES 7.84M
Contract
KES 3.38M
Spent
KES 3.33M
Utilisation
42.5%
Budget Utilisation
Components (1)
Component Budget Expenditure Status
construction of miting'ani sand dam KES 4.23M KES 4.23M Completed
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8693
  • WardUkia
  • Sub-CountyKaiti
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start10 Nov 2023
  • End26 Jan 2024
Timeline
Cabinet Paper Approved
Phase One · 18 Sep 2023
Approved Requisition
Phase Two · 25 Sep 2023
Floated
Phase Two · 06 Oct 2023
Awarded
Phase Two · 03 Oct 2023
Site Handover
Phase Three · 20 Nov 2023
Not Started
Phase Two · 20 Nov 2023
Ongoing
Phase Three · 01 Dec 2023
Completed
Phase Three · 01 Mar 2024