Kilala Bh Water Project

Completed GoMC-PMTS-2024-4639
Project Description

Extension of Mbalani Pipeline, Extension of Kilala Project line to Kyumu, Kyumu Water Kiosk, Mbalani Water Kiosk

Budget & Expenditure
Approved
KES 1.47M
Contract
KES 1.42M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-4639
  • WardUkia
  • Sub-CountyKaiti
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start15 Dec 2023
  • End31 Mar 2024
Timeline
Cabinet Paper Approved
Phase One · 18 Sep 2023
Approved Requisition
Phase Two · 25 Sep 2023
Floated
Phase Two · 27 Oct 2024
Awarded
Phase Two · 28 Nov 2024
Site Handover
Phase Three · 21 Dec 2020
Not Started
Phase Two · 21 Dec 2020
Ongoing
Phase Three · 02 Feb 2023
Completed
Phase Three · 12 Jun 2024