Water Improvement Programme

Completed GoMC-PMTS-2024-4873
Project Description

Installation of pumping system at Kithuni BH, Distribution

Budget & Expenditure
Approved
KES 700.0K
Contract
KES 700.0K
Spent
KES 2.30M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-4873
  • WardKee
  • Sub-CountyKaiti
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start01 Mar 2024
  • End01 Apr 2024
Timeline
Cabinet Paper Approved
Phase One · 06 Dec 2022
Approved Requisition
Phase Two · 04 Dec 2023
Refloated
Phase One · 19 Jan 2024
Awarded
Phase Two · 27 Feb 2024
Site Handover
Phase Three · 06 Mar 2024
Not Started
Phase Two · 06 Mar 2024
Site Handover
Phase Three · 06 Mar 2024
Not Started
Phase Two · 06 Mar 2024
Ongoing
Phase Three · 12 Mar 2024
Completed
Phase Three · 18 Apr 2024