Rehabilitation Of Nzalani Earth Dam- Scooping Of The Dam Construction Of Embankment Wall

Completed GoMC-PMTS-2024-7303
Project Description

Construction of Nzalani  Earth Dam; Embankment, Desilting of reservoir

Budget & Expenditure
Approved
KES 3.50M
Contract
KES 5.45M
Spent
KES 5.32M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-7303
  • WardKee
  • Sub-CountyKaiti
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start15 Apr 2024
  • End30 Aug 2024
Timeline
Cabinet Paper Approved
Phase One · 09 Nov 2023
Approved Requisition
Phase Two · 15 Dec 2023
Floated
Phase Two · 24 Jan 2024
Awarded
Phase Two · 28 Feb 2024
Site Handover
Phase Three · 11 Apr 2024
Not Started
Phase Two · 20 Mar 2024
Ongoing
Phase Three · 20 Apr 2024
Completed
Phase Three · 18 Apr 2024