Ithanzeni Borehole- Extension And Water Distribution

Completed GoMC-PMTS-2024-8137
Project Description

• Rising Main
• Ithanzeni Return Line
• Construction of 100CU.M Masonry Tank

Budget & Expenditure
Approved
KES 3.92M
Contract
KES 3.81M
Spent
KES 3.92M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8137
  • WardUkia
  • Sub-CountyKaiti
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
  • Start20 Jun 2023
  • End20 Oct 2023
Timeline
Cabinet Paper Approved
Phase One · 28 May 2023
Approved Requisition
Phase Two · 30 May 2023
Floated
Phase Two · 01 Jun 2023
Awarded
Phase Two · 20 Jun 2023
Site Handover
Phase Three · 20 Jun 2023
Not Started
Phase Two · 20 Jun 2023
Ongoing
Phase Three · 20 Jun 2023
Completed
Phase Three · 20 Oct 2023