Upgrading Of Mavindini Health Center

Completed GoMC-PMTS-2024-3586
Project Description

construction of Laboratory block 

Budget & Expenditure
Approved
KES 4.31M
Contract
KES 4.31M
Spent
KES 4.17M
Utilisation
96.8%
Budget Utilisation
Gallery (4 photos)
Mavindini : Construction Of Laboratory
Mavindini : Construction Of Laboratory
Mavindini
Mavindini
Mavindini
Mavindini
Mavindini
Mavindini
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3586
  • WardMavindini
  • Sub-CountyMakueni
  • DepartmentDepartment of Health Services
  • DirectoratePreventive and Promotive Services
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start27 Jun 2024
  • End25 Aug 2024
Timeline
Cabinet Paper Approved
Phase One · 21 Apr 2024
Approved Requisition
Phase Two · 06 May 2024
Refloated
Phase One · 06 May 2024
Awarded
Phase Two · 20 Jun 2024
Site Handover
Phase Three · 27 Jun 2024
Not Started
Phase Two · 27 Jun 2024
Ongoing
Phase Three · 28 Jun 2024
Completed
Phase Three · 15 Oct 2024