Upgrading Of Kyang’a Dispensary – Construction Of Staff Quarters

Completed GoMC-PMTS-2024-8746
Project Description

Construction of staff house

Budget & Expenditure
Approved
KES 3.43M
Contract
KES 1.89M
Spent
KES 3.21M
Utilisation
93.7%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8746
  • WardIlima
  • Sub-CountyKaiti
  • DepartmentDepartment of Health Services
  • DirectorateCurative and Rehabilitative Services
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start21 Dec 2023
  • End20 Mar 2024
Timeline
Cabinet Paper Approved
Phase One · 02 Nov 2023
Approved Requisition
Phase Two · 16 Nov 2023
Floated
Phase Two · 01 Dec 2023
Awarded
Phase Two · 20 Dec 2023
Site Handover
Phase Three · 03 Jan 2024
Not Started
Phase Two · 03 Jan 2024
Ongoing
Phase Three · 12 Jan 2024
Completed
Phase Three · 25 Jun 2024